1) Safety measures. After arriving at the construction site, we must first consider the width of the road, traffic and other factors. Make full use of safety facilities such as signs, warning lights, traffic cones, command flags, etc., and provide traffic controllers to manage pedestrians and traffic to prevent accidents. Construction personnel should wear work clothes with obvious signs and eye-catching colors. Night construction should have reflective clothing, reflective signs, to ensure the safety of construction personnel and engineering.
2. Lofting. First of all, traffic management should be done to ensure the safety of lofting operation.
Then measure the position of the marking line, and mark the road surface with measuring tools and paint according to the position and figure indicated in the design drawing. After the setting-out is completed, check whether the control meaning contained in the marking pattern can be correctly expressed and whether the driver and pedestrian can be accurately identified. When setting out the marking, the center point of the road shall be measured first, and then the center line shall be determined at intervals of 10-20M. Set the center point every 5-15m along the radius of curvature on the curve section. When it is confirmed that the set center point connection line matches the curvature, the road centerline profile is drawn by connecting each center point. In this way, check forward in sequence, while continuously extending the center line forward, it is also necessary to continuously check with the set center line position. According to the position of the road center line, mark half the width of the marking line and draw the outline of the width of the marking line for coating operation. For the curve section with small curvature radius, the design and construction of the road alignment must be confirmed to obtain the coordination with the road alignment.
3, the road surface cleaning. The important condition for the combination of paint and road surface is to keep the contact surface clean. The dust, mud and sand and moisture on the road surface are the main factors for the adhesion of paint. In particular, the slow lane and sidewalk pollution is serious, which is not only the dust on the road to be removed, but also pay attention to whether there is moisture, or whether the road is wet, if necessary, the application of gas flame heating and drying before construction.
A, first of all, the section to be marked to protect, so that the marking workers clean the road surface, the whole working section with broom, brush thoroughly clean up, accumulation with shovel.
B, brush off the dust on the road with an iron brush, and then clean the brush.
c. Blow the cleaned road surface 1-2 times with a hair dryer to completely remove the dirt in the road surface gap.
4, lane dividing line, edge line, can be measured according to the center line, the general situation also need to mark the width of the marking line. The setting-out of crosswalks and characters shall be based on the principle of construction drawing design.
5, spraying construction (see the operation of the marking machine).
6. Finishing. Trim the markings that do not meet the requirements, remove the overflowing and hanging coating film, check the size of the markings and the shape of the scribing, and modify the markings that do not meet the specifications. Timely arrange construction machinery, tools, remove construction residues and take photos.
operation of the marking machine:
1. Check: check the hydraulic oil of the paint pump, check the engine fuel and engine oil. The static oil level of hydraulic oil and engine oil should be located between the upper and lower scales of the scale. If it is insufficient, it should be supplemented. Check whether the screws of each connection part are loose and tightened.
2. Debugging: Open the front post, install the spray gun, adjust the spray gun and the post to be in a straight line, and adjust the spray gun to the required height.
3. Start-up: Stir the paint (road marking paint) evenly into the paint box, and insert the suction pipe of the high-pressure paint pump into the bottom of the paint box.
Open the drain valve of the high pressure paint pump;
Open the engine fuel tank switch, close the engine choke valve, and set the engine throttle to the low-to-medium speed position;
Pull the engine start handle by hand to start the engine;
Open the engine choke valve and run the engine at low speed for 3-5 minutes without load.
4. Cycle: The engine is set at a medium speed, the paint pump can suck the paint in 5-10 minutes, and then cycle for 3-5 minutes. When the temperature is low, the cycle time is appropriately extended.
5. Boost: close the drain valve and wait for 2-3 minutes until the pressure in the high-pressure pipeline reaches the requirements (common pressure 10-15Mpa), then construction can be carried out. Rotate the pressure regulating valve to adjust the working pressure, and rotate the pressure regulating valve clockwise to increase the pressure, otherwise the pressure decreases.
Warning: After the clockwise rotation of the pressure regulating valve stops, be sure to turn 1/4-1/2 turn counterclockwise, otherwise it will cause damage to the equipment.
6. Exhaust: After the hydraulic oil of the paint pump is too small or the paint pump is disassembled, air will enter the oil passage. At this time, the paint pump cannot normally inhale the paint and should be exhausted. The exhaust operation is as follows:
a Add hydraulic oil to the normal level;
B Remove the adjusting handle of the pressure regulating valve, and then you will see a black hexagon pressure regulating screw;
c Turn the pressure regulating screw counterclockwise to stop rotating when it is about to be unscrewed;
d Start the engine, hydraulic oil will flow out of the pressure regulating screw and there will be bubbles in the oil;
e After there is no bubble in the flowing hydraulic oil, gently tighten the pressure regulating screw clockwise, rotate 1/2 circle counterclockwise, install the adjusting handle of the pressure regulating valve, and complete the exhaust.
7. Spraying operation: Push the marking car forward to make the benchmark walk along the setting-out line, hold the control handle with your hand, spray gun to work, and start marking. Release the control handle and the spray gun stops working.
8. Adjustment: During construction, if there is a left-right deviation in the marking, the post and spray gun should be adjusted to the corresponding position. If there is a width error, the height of the spray gun from the ground should be adjusted. If it is high from the ground, the line width will be marked. Otherwise, the line will become narrower. When the nozzle is blocked, the nozzle rotating handle can be rotated 180 ° to spray the blockage, and then rotated back to continue construction.
9. Shutdown: Stop scribing. Open the drain valve, run the engine at low speed and no load for a while, turn off the ignition switch of the gasoline engine, and stop the engine. Suspension of construction can be exempted from this operation.
10. Cleaning: After working every day, use thinner to clean thoroughly, otherwise it will cause blockage and affect the next work. When not in use for a long time,
Oil should be sucked in after cleaning to avoid corrosion.
4. high pressure paint pump
1. The main machine of this marking machine adopts diaphragm type high pressure paint pump. The maximum flow rate is 8L/min; The common pressure is 10-15Mpa, and the maximum pressure can reach 25Mpa (about 250kg/cm2). The machine structure is simple, light and practical, easy maintenance.
2. Before using the paint pump, check whether the bolts and nuts are fastened. The paint pump uses 30# hydraulic oil, and each shift should be checked and added in time to make the oil level between the upper and lower scales of the oil dipstick.
3, paint must be kept clean, if there are impurities or particles should be first with 60-100 mesh filter can be used.
5. high pressure line and spray gun
1. High pressure pipeline
The high-pressure pipe consists of high-pressure hoses, joints and accumulators. The pressure in the high-pressure pipeline is as high as 20Mpa or above. It is strictly prohibited to disassemble and tighten screws before removing the pressure. The high-pressure hose is a synthetic resin steel wire braided hydraulic hose, which is corrosion-resistant and high-pressure resistant. The length of the high-pressure pipe is generally 2 meters. When writing and crosswalk lines, 10 meters long high-pressure hose can be used.
The joint is specially made of alloy material.
The accumulator is a high-pressure container, and its role is to ensure pressure stability, reduce pressure fluctuations, and ensure uniform marking pressure. In order to ensure that the accumulator has enough buffer space, the residual coating should be discharged after each shift is completed and the pressure is relieved.
2. Spray gun
This machine is equipped with a spray gun can also be used as a hand-held spray gun,
It is used for printing words, graphics, guiding instructions, etc.
3. Nozzle
This machine is equipped with a column-type rotary nozzle. In case of nozzle blockage, the knob can be rotated 180 degrees to spray the blockage, eliminating the trouble of cleaning and dredging when other types of nozzles are blocked, and improving work efficiency.
This machine is equipped with 17B/25 and 30/35 nozzles, 17 represents the flow 1.7L per minute, and 25 represents the spraying width of 25cm when the nozzle is 30cm from the road surface.
When stopping work, the nozzle knob should be rotated 90 degrees to be perpendicular to the nozzle,
Prevent misoperation and avoid condensation of marking paint in the nozzle.
6. power
Equipped with power LM/LL855 type for 5.5HP gasoline engine, LM890 type for 9HP gasoline engine. When starting, place the engine throttle in the low-speed position, turn on the ignition switch, and pull the start handle with your right hand to start. Then low-speed no-load operation for 3 minutes, then add the throttle, diaphragm pump work.
7. cleaning and maintenance
1. Try not to leave too much paint in the paint barrel after working every day. It is best to clean up the remaining paint in the barrel. Bearings and rotating parts should be regularly filled with grease and lubricating oil.
2, high-pressure paint pump and pipeline, etc., should be thoroughly cleaned at the end of the work every day. When not in use for a long time, a small amount of oil can be sucked into the machine after cleaning to prevent the paint pump and pipeline from rusting. The cleaning steps are as follows:
a Open the drain valve
B Lift the suction pipe from the paint tank to drain the paint in the machine c After confirming that there is no pressure, open the ball valve of the accumulator to drain the residual paint in the accumulator.
D will be inserted into the straw barrel for circulation, clean
e such as a cleaning is not clean, repeat the above steps can be thoroughly washed
f Clean the spray gun and nozzle and apply oil or immerse the nozzle in oil.
Technical guidance